Peter Black (NGNuk) Chair
Peter Ryde (NGNuk)
Mark Dalziel (NGNuk/OTA)
Rod Smith (NGNuk/OTA)
Angus Flett (BT Wholesale)
Andy King (Virgin Media)
Steve Unger (Ofcom)
Phil Kirby (Vodafone)
Neil McArthur (CPW)
Phil Male (Thus),
Apologies: Ben Philips ( Easynet), Stuart Shutt (Orange), Andy May (Cable & Wireless)
Minutes No changes to the draft minutes were requested. The minutes of the last meeting were therefore agreed.
Actions See outstanding actions at the end of this document.
At a prior Exec meeting an NICC/TSG statement proposed they will include in the NGN Interconnect specifications the requirement that:
The NGNuk Exec had asked the Secretariat to request from NICC information on the impact of their recommendation . The NICC response was as follows:
Question1 - What is the likely impact on channel density and consequently equipment cost?
Answer: Whilst comparable schemes have been implemented with minor impact by some DSP suppliers, the diverse sources of DSP software and hardware platforms means that NICC should not offer general advice. Operators must ask their suppliers for information.
Question 2 - Will the protocol RTCP HR be adopted universally by vendors - is there a split camp or are all the vendors thinking the same way?
Answer: We are not aware of any split, in that no DSP or gateway vendor has opposed the progress being made with RTCP HR or H.248.48. Early customer interest in, and demand for, the feature is likely to speed up introduction. However, once again operators must ask their suppliers for information
Question 3 - For operators who already have investments in creating NGN architectures what is the likely impact of an upgrade?
Answer: Most telco-scale equipment can be upgraded, usually remotely. However, operators should check this point with their suppliers.
Question 4 - The monitoring will generate messages which will require storage and processing likely volumes, size of message?
Answer: In a typical use of RTCP HR/H.248.48, the largest number of such reports in a single Subtract response is 4, so an IP-IP gateway (two Subtract responses per call) could generate maximum about 2k octets of data per call. Whole UK PSTN size is of order 2E6 Erlangs busy hour, or 2E4 calls/s, so could generate 4E7 (40Mbytes) data per second or 3 Tbytes/day. This has taken several worst-case assumptions, and the key to limiting it is to store & process data only by exception parameters.
The Exec were unhappy that NICC had been unable to provide greater context or quantification. The NGNuk Secretariat were asked to speak to NICC to obtain some level of quantification of the impact.
Action 1 27/09/2007 The Secretariat to seek further clarification and quantification of the likely impact and costs resulting from the NICC decision to adopt RTCP HR for the monitoring of all calls.
Peter Ryde reported back that limited responses had been given to the questions on call control and session management and on developing the templates that had been circulated following the previous commercial work group meeting.
Thus had provided the most detailed response on the Call Control/ Session management question. Having reviewed this issue in more detail, Thus are less concerned that session management / call control will be a significant cost in PSTN replacement services and hence likely to require that they be separately identified and charged for. However for non PSTN services there may be situations where the session management elements are used disproportionately (or even abused) such that some mechanism to restrict their use is required. In Thuss view an economic control in the form of a cost mechanism would be the most effective. This could be set to zero or the session management elements bundled with another more material cost element for those services (e.g. PSTN voice) where the cost of session management is less important. Therefore Thus recommend that session management and call control should be charged separately.
The responses will be circulated to the Commercial work group for information.
A small group of individuals had developed some straw men of the possible charging scenarios for discussion. Their intent was to present these straw men and take feedback, not from the point of view of what permutation of the options people want, but from the point of view of what the permutations could be.
Following discussion within the work group it was agreed as being that the group would identify whether any further permutations were required from those identified to date. (Note: none were identified at the meeting)
The options would be developed further with respect to the pros and cons , variables ,issues and costs etc:
Once these Straw men had been developed further the suggestion was that they would be distributed for formal responses from CPs regarding which approaches the supported and why. The intent was to try to build consensus around an approach by Christmas.
It was agreed that it would be valuable that the work be more formally documented to ensure consistency across the straw men such that issues such as costs, migration , economic benefits etc are consistently addressed. There were no volunteers for this work and it was suggested that this would be an appropriate task for a suitably qualified 3rd party.
This approach was endorsed by the Exec
Action 5 31/05/2007 had given the action to the Secretariat to create a straw man structure that replicates the final interconnect framework and to populate this document and identify clearly what has been agreed and the key issues outstanding.
The straw man was distributed to the Commercial work group on 15th August and to the Exec prior to the August meeting.
No comments were received. However this the document was reviewed with Commercial Group 24th September via an audio call.
The commercial work group agreed the following:
Action 2 27/09/2007 Peter Ryde to define more clearly the issues involved and recommend the level of Programme Management that is appropriate
The Exec then discussed in more detail the specific areas covered within the document:
Legal
This is work stream represents the legal drafting work to develop the new framework
As initial NGN contract activity through Consult 21 is likely to be between BT and other CPs and that the MSA discussions are being co-ordinated by UKTA it is proposed that this activity is also managed by UKTA (however, the involvement of the Mobile Operators needs to be considered)
Action 3 27/09/2007 - Peter Ryde to meet with suitable representatives of UKTA to discuss the NGNuk view regarding the approach to developing the legal element of the NGN interconnect contract from UKTA work with Consult21 and also how to ensure Mobile Operators engagement in this process
Action 427/09/2007- The Exec specifically requested that all Mobile Operators were alerted to this approach.
Definitions
The NGNuk Exec had previously proposed that a standard set of definitions should be used in order to remove ambiguity. As an example, members have not been able to agree on the use of:
If undertaken should be owned by NGNuk but should be undertaken in conjunction with UKTA, however it requires a clearer definition of the areas to be covered to avoid duplication or unnecessary cost. The view of the commercial work stream had been that whilst this what felt to be a useful and valuable contribution but did not feel that it was a priority for NGNuk.
The Exec however felt more strongly about the matter. They felt that work was required in two areas: Firstly that agreement around the commercial terms and definitions used in any agreements (contractual or otherwise) would minimise confusion and disputes in future. In addition it was also felt that a set of principles was required reflecting the aims and ambitions of the industry in terms of the service it delivers to users. This was felt important as these would flow through to the interconnect agreements and implementation of interconnects themselves by defining what was measured, how it was measured and how processes should operate. Whilst it would not attempt to define the detail it should aim to establish a reference against which implementation can be judged. This was agreed as being something that should be undertaken at Exec level.
Action 5 27/09/2007 Secretariat to develop scoping document for those commercial areas requiring agreed definitions. This to be reviewed with UKTA . Following review to be represented to the Exec with a resource plan (and costs)
Action 6 27/09/2007 The secretariat to request feedback from the Exec members on their thoughts regarding the key aims and attributes of the service principles. These to be collated by the secretariat and represented for discussion at the October Executive meeting.
Charging
The charging principles identified in the NGNuk Commercial activity stream will drive the charging methods/models and pricing arrangements on NGN interconnects.
NGNuk was agreed as the current owner, until early 2008 at the latest, when the responsibility should be transferred to a suitable organisation for any outstanding detail
Billing and Payment Processes
This is an activity stream to develop the operational processes for billing and payment , manuals etc.
This level of detail is inappropriate to NGNuk and will also extend well beyond the anticipated end date of NGNuk. The NICC business-to-business group already have work underway in this area and would appear to be the appropriate owner
Note: As part of the charging activity there needs to be a review of the feasibility and impact of the charging recommendations on billing systems and billing development.
Action 7 27/09/2007 - Peter Ryde to meet with suitable representatives of NICC B2B work group to discuss the NGNuk view regarding the approach to developing the detailed billing processes and confirm that NICCB2B believe that they are the suitable owners of such activity.
Telephony Emulation
This work stream covers the development of the service specification for Telephony Emulation, including related aspects such as CLI and Transfer charging.
As this activity is already underway to support the immediate requirements of the Consult 21 process the activity should vest with Consult21/NICC and then be adapted for bilateral use.
Numbering and Addressing
A number of parties are now active in the area of Numbering and Addressing with many of the commercial issues surrounding the establishment , use and access to the Central Data Base now likely to reside with the organisation the Ofcom will appoint to undertake this work. It was not felt that any detailed implementation activity was required by NGNuk however the Exec felt that agreement to an overall approach and direction by Industry would be of benefit.
Action 8 27/09/2007 The secretariat to request feedback from the Exec members on their thoughts regarding the key aims and attributes of the principles that need to be considered for Numbering and Addressing. These to be collated by the secretariat and represented for discussion at the October Executive meeting.
Quality of Service
NGNuk Interconnect Requirements proposed a QoS schema, to be validated by NICC. This will significantly influence service definitions, pricing and other commercial aspects. The objective of this work stream is to determine the QoS schema to be used on NGN interconnections in the UK.
It was agreed that following the initial iteration between NGNuk and NICC, this will be a NICC responsibility as this is clearly a technical standards matter.
Network (and Transport) Layer
NGNuk interconnect requirements proposed a layered framework for the interconnection architecture, comprising:
This work stream aims to define the contract annex(es) which specify the standards to be used in the Framework
As most of this work is already underway as part of Consult21 the Exec agreed that it should be owned by NICC/Consult21 and adapted for bilateral use by individual CPs.
Control ( and Intelligence) Layer
This work stream is intended to define the control and intelligence layer standards to be used. Unlike the Network layer, this layer is much less well-defined as it will utilise standards and techniques which are still emerging and for which there is limited practical experience in both vendor and supplier communities.
The Exec agreed that NICC is to lead however there is likely to need for significant NGNuk input as policy options related to presence, security and authentication emerge. Improved dialogue and co=ordination were stressed as imperative to this.
Data (Ethernet)
In the layered approach, Data (Ethernet) will here be defined as an application
It was agreed that NGNuk should conclude the drafting of the current service requirements document, and forward this to NICC to review and subsequently specify the technical requirements of the service.
Action 9 27/09/2007 Peter Ryde to forward completed Data Requirements document to NICC
Planning and Operations
Once the services and technical standards are stable the operational procedures and agreements need to be defined.
This work logically fits in the NICC business-to-business standards group but will require significant involvement of UKTA. Whilst much of the Industrys efforts might be focussed on the contractual arrangements with BT, the framework should recognise that administrative and operational arrangements between other operators may not need to be as complex .This general point may also apply to other activity streams.
Action as 7 above
Service Level Agreement
It has been assumed that an overall SLA for the contract will be agreed augmented, as necessary, by service specific elements that will identify elements unique to each service. This work stream is designed to develop the overall SLA
Whilst UKTA is well placed to lead , due to its involvement with the current Consult21 process , there was some discussion within the Commercial Group regarding whether NGNuk show establish the broad framework and principles under which the SLA will operate across industry. This was agreed by the Exec.
Action as 6 above
NICC requested to comment on NGNuk requirements documentation, however only BT have responded to date:
BT considers that considerable further work is required before the document can be considered to fulfil its objective of defining NGN interconnect service requirements. One of the planned uses of this document by NICC is to allow them to develop the necessary NGN interconnect standards to support the defined service requirements. BT considers that the document is still a long way for meeting this planned objective, though BT welcomes the established liaison between NGNUK and NICC on this subject as there will need to be a number of iterations between the technical experts in NICC and the commercial requirements development in NGNUK before this document can be finalised.
The following list of comments are examples of where BT believe the document is deficient:
Action 10 - 27/09/2007 Secretariat to follow up with NICC to obtain collective response from NICC regarding the Requirements submitted by NGNuk.
The Voice PID outlines the purpose of the work stream as developing a specification for Real Time Voice (PSTN/ISDN) reference offer for interconnected NGNs with a major deliverable as one or more technical interconnect specifications to support the agreed reference services.
Given the resourcing of current NGNuk work streams to date it was agreed that CPs were unlikely to be able to support this activity (due to both the availability and prioritisation of resources).
It was felt that whilst this work will need to be undertaken it is unlikely to have sufficient impetus until such time as interconnection with BT 21CN becomes imminent.
The topic had been discussed briefly at the August Executive meeting and Action 1 30/08/2007 requested that the Secretariat suggest a form of words which the Exec could endorse agreeing the approach. The following was proposed:
The members of NGNuk understand that to facilitate CP to CP interconnection a significant level of detailed work will be required both technically and commercially. It is further recognised that considerable resources are being deployed on Voice interconnect through industry support of Consult 21 process with BTW. To avoid unnecessary duplication and to avoid potential confusion the members of NGNuk have agreed that other than the commercial framework itself, further work on Voice within NGNuk will be suspended pending progress between industry and BTW via Consult 21. It is anticipated that CP to CP interconnection will subsequently build upon some agreed subset of those agreements, principles, service descriptions etc that are agreed between industry and BT through Consult 21.
Action 11 27/10/2007 Peter Ryde to distribute the proposed wording on the approach to Real Time Voice to the Executive for comment
Data Interconnect Requirements V3.2 has been agreed by the working group to reflect the VPN requirements articulated during MPLS debate.
Wider member review will be undertaken in parallel to NICC activity as most interested parties have been involved.
This will be sent to NICC imminently, however it the input is unlikely to be utilised prior to the Orange release.
Action as 8 above
See section 4 above
BTW have provided lead (Ryan Hardy) who has drafted a paper provided to the Secretariat for comment. This will be circulated to members for comment w/c 1st October.
It was noted that Presence and Location will have an impact on the Security and Authentication work stream (as will Numbering and Addressing)
The workshop took place in August and generated considerable debate. The primary issue of contention was to what extent the operators should be responsible for identifying the individual rather than the device initiating a session. The business case will need to be made by each operator separately however it would seem sensible for the underlying processes and protocols to support identification of individuals as well as devices.
The Minutes of work group circulated have been circulated to members but no further comments received
The next step is to engage with the vendors to ensure that industry is aware of (and making the best use of ) the available technologies and to inform NGNuk understanding of likely timescales for delivery of key elements.
The next work group review is not anticipated prior to November
Simon Williams ( Senior Product Manager) at Ethernet attended to provide an overview of the development of the Openreach Ethernet Portfolio
Action 12 27/09/2007 Peter Black and Steve Unger agreed to review the options on the future of NGNuk for consideration by the Executive and wider membership.
The next meeting will be 10.00 to 14.00 on 25th October at Riverside House.
Future scheduled meetings
DATE | MEETING | TIME |
29th November 2007 | NGNuk Executive Meeting | 10.00 14.00 |
13th December 2007 | NGNuk Executive Meeting | 10.00 14.00 |
Peter Ryde
NGNuk Office
07771 555 048
020 7783 4688
Action 14 29/03/2007 - Develop guidance notes for work stream leaders regarding the use of non members within a work stream. As there is no external participation it is suggested that this action is suspended until ( or if required) | Peter Ryde Closed |
Action 3 26/04/2007 Secretariat to arrange that Openreach attend to provide detail of where the Openreach products will interconnect. Openreach attended the September Exec meeting | Secretariat Closed |
Action 5 31/05/2007 Secretariat should create a strawman structure that replicates the final interconnect framework, then to populate this document to identify clearly what has been agreed and the key issues outstanding. Update on progress given to the Exec meeting | Secretariat Completed |
Action 1 - 28/06/2007 - Gideon Senensieb to provide NGNuk with a structured set of questions reflecting the specific feedback Ofcom is seeking from CPs to help ensure that the assumptions adopted are as robust and accurate as possible. Peter Black to follow up with Ofcom. | Ofcom Ongoing |
Action 1 - 26/07/2007 - Numbering and Addressing ( Ben Philips, Sky/Easynet ) Requires review with NICC lead to ensure approaches are consistent. Ben Phillips to pick up the issue with Nigel Titley and liaise with Paul Rosbotham. Superseded by action 8 of 27/09/2008 | Ben Phillips Closed |
Action 4 26/07/2007 NGNuk to request from NICC information on the impact of their recommendation | Mark Dalziel Completed |
Action 1 30/08/2007 Peter Ryde to draft agreement relating to approach to Voice activity building upon C21 and circulate this prior to September Exec. | Peter Ryde Completed |
Action 2 30/08/2007 Stuart Shutt to forward contact details for the Liberty Alliance to Peter Ryde. | Stuart Shutt Ongoing |
Action 1 27/09/2007 The Secretariat to seek further clarification and quantification of the likely impact and costs resulting from the NICC decision to adopt RTCP HR for the monitoring of all calls. | Secretariat |
Action 2 27/09/2007 Peter Ryde to define more clearly the issues involved and recommend the level of Programme Management that is appropriate | Peter Ryde |
Action 3 27/09/2007 - Peter Ryde to meet with suitable representatives of UKTA to discuss the NGNuk view regarding the approach to developing the legal element of the NGN interconnect contract from UKTA work with Consult21 and also how to ensure Mobile Operators engagement in this process | Peter Ryde |
Action 427/09/2007- The Exec specifically requested that all Mobile Operators were alerted to this approach involving UKTA to develop the legal element of the inter CP contract. | Peter Ryde |
Action 5 27/09/2007 Secretariat to develop scoping document for those commercial areas requiring agreed definitions. This to be reviewed with UKTA . Following review to be represented to the Exec with a resource plan (and costs) | Secretariat |
Action 6 27/09/2007 The secretariat to request feedback from the Exec members on their thoughts regarding the key aims and attributes of the service principles. These to be collated by the secretariat and represented for discussion at the October Executive meeting. | Secretariat |
Action 7 27/09/2007 - Peter Ryde to meet with suitable representatives of NICC B2B work group to discuss the NGNuk view regarding the approach to developing the detailed billing processes and confirm that NICCB2B believe that they are the suitable owners of such activity | Peter Ryde |
Action 8 27/09/2007 The secretariat to request feedback from the Exec members on their thoughts regarding the key aims and attributes of the principles that need to be considered for Numbering and Addressing. These to be collated by the secretariat and represented for discussion at the October Executive meeting. | Secretariat |
Action 9 27/09/2007 Peter Ryde to forward completed Data Requirements document to NICC | Peter Ryde |
Action 10 - 27/09/2007 Secretariat to follow up with NICC to obtain collective response from NICC regarding the Requirements submitted by NGNuk. | Secretariat |
Action 11 27/10/2007 Peter Ryde to distribute the proposed wording on the approach to Real Time Voice to the Executive for comment | Peter Ryde |
Action 12 27/09/2007 Peter Black and Steve Unger agreed to review the options for the continuation of NGNuk for consideration by the Executive and wider membership. | Peter Black Steve Unger |